INVESTMENT POLICY
INVESTMENT PROCESS IN INDUSTRIAL PARK
DETAILED PROCESS
Investment steps | Implementation work | Time, cost |
Step 1: Customers search for investment information | Based on the approved planning, the Investor inquires about information and selects the location of the land plot. | - Fees: none |
Step 2: Sign the land lease principle contract.
|
After directly negotiating with VL2 Industrial Park on the area, location of the land lot, payment method, the Investor signs a preliminary land use right lease principle contract with Vinh Loc 2 and pay deposit to keep the land. | - Fees: none |
Step 3: Business registration (for domestic enterprises). |
Vinh Loc 2 cooperates with the Investor to carry out the necessary documents to apply for a business license at the Department of Planning and Investment of Long An. | - Duration: 03 days - Fees: according to regulations of Long An Department of Planning and Investment |
Step 4: Issuance of investment certificate (for enterprises with foreign elements). | Vinh Loc 2 cooperates with the Investor to complete the necessary documents to apply for an investment certificate in Laeza | - Duration: 10 days - Fees: none |
Step 5: Notarization of official land lease contract. | Both sides sign the official Land Lease Contract, then notarize it at the Notary Office. | - Duration: 01 day - Fees: according to regulations. |
Step 6: Issuance of construction permission. | Vinh Loc 2 cooperates with investors and outsourcers to apply for a construction permission in Laeza | - Duration: 20 days - Fees: according to regulations of the Department of Construction |
Step 7: Issuance of land use rights. |
After the Investor fully pays the land rent, Vinh Loc 2 will assist the Investor in carrying out the procedures to apply for a Land Use Right Certificate (red book). | - Duration: 17 days - Fees: according to regulations of the Department of Natural Resources and Environment |
Step 8: Issuance of ownership for the construction. | After the construction is completed and the Investor has been granted a land use right certificate, Vinh Loc 2 will assist the Investor in the procedure to apply for a Certificate of Ownership for the Construction (pink book). | - Duration: 30 days - Fees: according to regulations of the Department of Natural Resources and Environment |