INVESTMENT POLICY

INVESTMENT PROCESS IN INDUSTRIAL PARK



DETAILED PROCESS

Investment steps Implementation work Time, cost
Step 1: Customers search for investment information Based on the approved planning, the Investor inquires about information and selects the location of the land plot. - Fees: none
 
Step 2: Sign the land lease principle contract.
After directly negotiating with VL2 Industrial Park on the area, location of the land lot, payment method, the Investor signs a preliminary land use right lease principle contract with Vinh Loc 2 and pay deposit to keep the land. - Fees: none
 
Step 3: Business registration (for domestic enterprises).
 
Vinh Loc 2 cooperates with the Investor to carry out the necessary documents to apply for a business license at the Department of Planning and Investment of Long An. - Duration: 03 days
- Fees: according to regulations of Long An Department of Planning and Investment
Step 4: Issuance of investment certificate (for enterprises with foreign elements). Vinh Loc 2 cooperates with the Investor to complete the necessary documents to apply for an investment certificate in Laeza - Duration: 10 days
- Fees: none
Step 5: Notarization of official land lease contract. Both sides sign the official Land Lease Contract, then notarize it at the Notary Office. - Duration: 01 day
- Fees: according to regulations.
Step 6: Issuance of construction permission. Vinh Loc 2 cooperates with investors and outsourcers to apply for a construction permission in Laeza - Duration: 20 days
- Fees: according to regulations of the Department of Construction
 
Step 7: Issuance of land use rights.
After the Investor fully pays the land rent, Vinh Loc 2 will assist the Investor in carrying out the procedures to apply for a Land Use Right Certificate (red book). - Duration: 17 days
- Fees: according to regulations of the Department of Natural Resources and Environment
Step 8: Issuance of ownership for the construction. After the construction is completed and the Investor has been granted a land use right certificate, Vinh Loc 2 will assist the Investor in the procedure to apply for a Certificate of Ownership for the Construction (pink book). - Duration: 30 days
- Fees: according to regulations of the Department of Natural Resources and Environment